Add phased plan for realistic steam/enthalpy modeling
This commit is contained in:
5
TODO.md
5
TODO.md
@@ -7,3 +7,8 @@
|
|||||||
- [ ] Introduce CHF/DNB margin, clad/fuel split temps, and SCRAM matrix for subcooling loss or SG level/pressure trips.
|
- [ ] Introduce CHF/DNB margin, clad/fuel split temps, and SCRAM matrix for subcooling loss or SG level/pressure trips.
|
||||||
- [ ] Flesh out condenser behavior: vacuum pump limits, cooling water temperature coupling, and dynamic back-pressure with fouling.
|
- [ ] Flesh out condenser behavior: vacuum pump limits, cooling water temperature coupling, and dynamic back-pressure with fouling.
|
||||||
- [ ] Dashboard polish: compact turbine/generator rows, color critical warnings (SCRAM/heat-sink), and reduce repeated log noise.
|
- [ ] Dashboard polish: compact turbine/generator rows, color critical warnings (SCRAM/heat-sink), and reduce repeated log noise.
|
||||||
|
- [ ] Incremental realism plan:
|
||||||
|
- Add stored enthalpy for primary/secondary loops and a steam-drum mass/energy balance (sensible + latent) while keeping existing pump logic and tests passing.
|
||||||
|
- Adjust HX/pressure handling to use stored energy (saturation clamp and pressure rise) and validate steam formation with both pumps at ~3 GW.
|
||||||
|
- Update turbine power mapping to consume steam enthalpy/quality and align protection trips with real steam presence.
|
||||||
|
- Add integration test: cold start → gens/pumps 2/2 → ramp to ~3 GW → confirm steam quality threshold → enable all turbines and require electrical output.
|
||||||
|
|||||||